Plan To Learn

OpenAgile CorePractices: PlanToLearn

Every type of work is governed by a Horizon of Predictability. Any plan that extends beyond this horizon of predictability is bound to fail. Agile work uses an explicit learning cycle tied in with the planning of work to accomodate this inevitable change.

First, a goal is required. This goal can be long-term. Teams using Agile Work then create a queue of work items to be done in order to reach this goal. Each iteration, some of these items are selected, finished and then the queue is adjusted. The changes in the work queue are based on external factors, and learning that the team does as it goes.

One of the most effective methods for the team to learn about how it is doing its work is the retrospective. After each delivery of results, the team holds a retrospective to examine how it can improve.

Also Known As: Inspect and Adapt (Scrum), Kaizen (Lean), Adaptive Planning (generic).